Tuesday, November 22, 2016

If you do not stop the risk of a new gas unit Ghorashal

Ghorashal 365 MW of new combined-cycle power plants (sisipipi) under the direction of the gas that will be required, but there was uncertainty about getting to Petrobangla.Dual fuel (gas and oil) resources become ineffective due to lack of gas supply to shut down the plant said Wednesday the Ministry of Planning Implementation Monitoring and Evaluation Division (IMED).The new unit of 365 MW of electricity per day will be required for the production of 65 million cubic feet of gas.Gas crisis forced the government to produce electricity from gas-fired power plants as well as oil-based power plants. But the only gas station. The constantly increasing demand for gas, decreasing production. Gas crisis in the existing plants is not running properly. Yet gas power plants under construction.Aiemaidira official said, according to the power station's ability to manage the supply of gas to the pressure required to ensure that the ministry and the department has recommended IMED. Declining gas reserves in order to consider the next phase dual fuel use has ordered.IMED sources, the report has sisipipi spot around aiemaidira director (energy) Mohsin Nasima. IMED report mentions various problems.The report also found that aiemaidira of power, from the beginning of the problem has been to build the plant. Ibhakuyesanera generated electricity will be required for the two Bay. Although there has not been created yet another one of the Bay.014 ongoing projects in the period from January to December 016. But the project was approved on 8 April 014. Anumodanakale the implementation of the project for 3 months before the start of the decline to determine the overall progress.The overall implementation of the project targets were not achieved. 201516 fiscal year until the project's estimated cost of 51 thousand crore. Progress has been made but only 840 million, which is 33 percent to 44 percent.The report showed aiemaidira information regarding the procurement, purchase package contract until 2018. However, the duration of the project until December 016. Found, within the prescribed period for the project, transformers, 230 kV sub-stations and water treatment plants can not be bought.When completed construction of a new unit Electric Power Natural gas will be used as a raw material. The new unit will be able to pay for gas, according to Petrobangla now. However, officials said the project, Ghorasal unit 017 in one and two will be closed. The new unit will be the unit with gas.Abul Kalam Azad, deputy director of the project said, "The new unit Ghorashal day to 65 million cubic feet of gas.There was uncertainty about getting out of the Petrobangla. However, even if the gas power plant will not be closed. Because, if you do not Petro gas, then we run the old unit of gas for the new unit. However, we agree with the report aiemaidira.

No comments:

Post a Comment